Yapı Denetimi: Who Actually Inspects a New Build in Turkey

New Builds · Construction Quality · Updated October 2026

Yapı Denetimi: Who Actually Inspects a New Build in Turkey

Every permitted building in Turkey above a certain size has to be supervised by an independent, state-licensed firm that is paid by the owner and liable for structural defects for fifteen years. Knowing who that firm is — and whether your building was even inside the system — is one of the most useful checks a foreign buyer can run.

🏗️ Law 4708, in force since 13 July 2001
📜 15-year structural liability
⚠️ Small villas can fall outside it
15 YearsLiability For The Load-Bearing System
2 YearsLiability For Non-Structural Parts
200 m²Threshold Below Which Small Builds Are Exempt
3 DaysTo Report Any Deviation From The Permit
Start Here

The developer builds it. Someone else is supposed to check it.

When a foreign buyer looks at a new apartment in Turkey, the names that come up are the developer and the agent. Neither of them is the party whose job it was to verify that the building was actually constructed to its approved drawings. That job belongs to a yapı denetim kuruluşu — a building supervision company — and it is a separate legal creature with its own licence, its own liability and its own file on your building.

The system was created by the Building Supervision Law, Law No. 4708, passed on 29 June 2001 and published in the Official Gazette on 13 July 2001 (issue 24461), and amended many times since — most recently by Law No. 7579 of 7 May 2026. Its stated purpose, in Article 1, is to secure life and property by providing design and construction supervision so that buildings are built to the development plan and to the rules of science, art and health.

What makes this worth a foreign buyer’s attention is Article 3. Supervision firms, their inspecting architects and engineers, the project designers, the laboratory staff and the contractor are all liable — in proportion to their fault — to the building owner and to the permitting authority for defects caused by work that departs from the permit or from proper practice. That liability runs from the date the occupancy permit was issued, and it lasts fifteen years for the load-bearing system and two years for everything else.

Why this matters when you buy a resale: the fifteen-year clock starts at the building’s occupancy permit, not at your purchase. A six-year-old apartment still has roughly nine years of structural liability attached to it. Finding out which firm supervised the build, and whether that firm is still licensed, tells you whether that protection is worth anything in practice.

This guide covers who the parties are, how the firm is appointed and paid, what it must actually do, which buildings are quietly left outside the system, and what changed in 2026. For the wider purchase sequence see our Turkey property buyer’s guide, and for the permit that starts the liability clock, our guide to the habitation certificate (iskan).

Law 4708 — At A Glance

The building supervision framework, as amended to 2026

LawNo. 4708
Passed29 June 2001
Official Gazette13 July 2001, No. 24461
Supervising ministryEnvironment, Urbanisation & Climate Change
Structural liability15 years from occupancy permit
Other parts2 years
Firm ownership100% architects / engineers
Owner picks the firmUp to 500 m² only
Above thatMinistry assigns electronically
Latest amendmentLaw 7579, 7 May 2026
The exemption to check first. A detached building of no more than two storeys above the basement, with a total construction area not exceeding 200 m², sits outside Law 4708 altogether. Many standalone villas fall into this band. Supervision there is handled under the Development Law instead, by an architect or engineer taking on technical responsibility — not by a licensed supervision company with a fifteen-year statutory liability.
The Cast

Six parties, and why the separation is the point

Law 4708 defines each role deliberately, because the whole design depends on keeping them apart. These are the words you will meet in a project’s paperwork.

  • Yapı sahibi — the building owner. If you buy off-plan, the developer is usually the yapı sahibi during construction, not you.
  • Yapı müteahhidi — the contractor that undertakes the work, registered with the relevant professional chamber.
  • Proje müellifi — the project designer who prepares the building’s studies and drawings.
  • Yapı denetim kuruluşu — the supervision company: a ministry-permitted legal entity that does supervision and nothing else, with architects and engineers as its only partners.
  • Denetçi mimar ve mühendis — the inspecting architects and engineers, individually certified by the ministry.
  • Laboratuvar — a ministry-permitted testing facility for soil and building materials.

Two rules in Article 2 do most of the protective work. First, the supervision contract is signed between the firm and the building owner or the owner’s proxy — and the owner may not appoint the contractor they hired for the construction work as that proxy. The party being checked cannot arrange its own check. Second, a supervision company may not engage in any commercial activity other than supervision, and its inspecting architects and engineers are barred from other professional or construction-related commercial activity while they are supervising.

What to ask a developer. “Which yapı denetim kuruluşu supervised this block, and may I see the supervision contract and the completion report?” A developer selling a legitimately supervised building answers that in a sentence; reluctance is itself information. See also how to check a Turkish property developer.
Article 2

What the supervision company is actually required to do

These are statutory duties, not service-brochure promises. Each one leaves a document behind, which is what makes them checkable years later.

📐

Review the design before a brick is laid

Examine the soil and foundation reports and the designer’s application drawings, check the drawings and calculations, and report conformity to the permitting authority — without the file passing through any other body’s approval.

📅

Register the undertaking within seven days

File a formal undertaking with the permitting authority confirming it has taken on supervision, and notify the ministry of the building’s details within seven days of the construction permit being issued.

🔍

Supervise against the permit

Check that the building is constructed in conformity with the permit, its annexes and the legislation. This is the core duty, and the one a defect claim is usually built on.

🧪

Test the materials and document it

Verify that materials and workmanship conform to the drawings, technical specification and standards, have the tests done at permitted laboratories, and certify the results. Where materials fail, report it to the permitting authority and the provincial industry and trade directorates.

⚠️

Report deviations in three working days

If work departs from the permit or its annexes, notify the permitting authority within three working days — a short, hard deadline, and a useful thing to look for in a building’s file.

Sequence

How a building passes through the system

Simplified, but in the statutory order. Understanding the order is what lets you spot a step that was skipped.

1

A supervision company is appointed

Where the construction area on which the contract fee is based is up to 500 m², the owner chooses the firm. For anything larger the ministry determines up to two firms electronically, ranked first and second, taking into account how many are active in that province, and the owner contracts with one of them. This allocation rule was rewritten by Law 7534 on 5 December 2024.

2

The contract is signed and filed

The contract sets out the subject, location, construction area and duration of the service, the building’s physical characteristics as agreed between owner and contractor, the fee, and the technical staff who will work on it. A copy goes to the permitting authority with the undertaking, and the contract cannot be terminated except in cases the ministry has defined.

3

The fee goes into a held account, not to the firm

The owner pays into a trust-type account at the provincial accounting unit, from which the firm is then paid. Of the amounts deposited, 3% goes to the authority that issued the permit and 3% to the ministry’s revolving fund. The firm may not ask the owner for any further payment under another heading.

4

Design review, then staged site supervision

The firm reviews the reports and drawings, reports conformity, then supervises on a risk-based basis — a principle added to Article 3 in February 2018 — testing materials through licensed laboratories as the structure goes up.

5

Completion is reported, and the clock starts

The firm reports to the permitting authority that the building has been completed, in whole or in part, in conformity with the permit drawings. The occupancy permit follows, and its date is when the fifteen-year and two-year liability periods start to run.

6

A building identity certificate is affixed

Buildings supervised and completed under Law 4708 receive a bina kimlik sertifikası — a building identity certificate, introduced in June 2022 and fixed to the building, so that its technical and general information can be reached by the owner, interested citizens and public officials through modules the ministry authorises.

Scope

Inside the system, or outside it?

Article 1 lists what Law 4708 does not cover. For a buyer, the exemptions matter more than the inclusions — because an exempt building has no supervision company standing behind it.

ساختمان Supervised under Law 4708? What applies instead
Apartment block requiring a construction permit, inside or outside municipal boundaries بله Licensed supervision company, 15-year structural liability
Detached building, max two storeys above basement, total construction area not over 200 m² نه Technical responsibility assumed by an architect or engineer under the Development Law
Several detached buildings on one parcel with a combined area over 200 m² بله The law applies to the parcel even though each building is small
Housing in village settlement areas and non-settlement areas outside municipal limits, or in municipalities under 5,000 population: max two storeys, up to 500 m² نه Outside the law, together with their coal stores, parking and depots
Agricultural and livestock buildings that are not integrated facilities نه Excluded by Article 1
Solar power plants and wind power plants نه Excluded by the amendment of 5 December 2024
Public buildings and facilities under Article 26, and buildings not subject to a permit under Article 27, of the Development Law نه Excluded by Article 1

Read that second row again if you are buying a standalone villa. A two-storey house under 200 m² is a very common product on the Turkish coast, and it is exempt. That does not make it badly built — technical responsibility still has to be assumed by a qualified architect or engineer, and the building still needs a permit and an occupancy certificate. But the fifteen-year statutory liability of a licensed supervision company is not part of the package, and a buyer who assumes it is has mispriced the risk. The third row is the counterweight: where one parcel holds several detached buildings whose combined area exceeds 200 m², the law applies anyway.

Where supervision liability stops. Article 3 is explicit that if substantial alterations are made after the occupancy permit without the authority’s consent, the person who made them is liable for the resulting damage — not the supervision company. A heavily remodelled resale can therefore have had its structural protection quietly transferred to whoever knocked the walls through. The firm is also not liable for damage from landslides, avalanches, rockfalls or floods originating outside the parcel where the owner ignored a written warning.
Fees

What supervision costs, and why it is capped

The fee is set in the supervision contract, but Article 5 fixes the rates rather than leaving them to negotiation. They are a percentage of the building’s fee-basis approximate cost — the construction area multiplied by unit costs the ministry publishes by regulation.

Where the fee-basis construction area is up to and including 1,000 m², the fee is 1.75%. From 1,001 m² up to and including 50,000 m² it is 1.5%, and above that 1.25%. Where the work is not subject to electronic allocation the rate may rise to a maximum of 3.50%, and it increases by 5% annually where construction runs beyond one year. For strengthening works the fee may not be less than 25% of the fee for the whole building.

Buildings inside the approved boundaries of industrial zones, technology development zones, organised industrial zones, free zones and industrial sites get a discount of up to 50%. The fee covers ministry-specified laboratory tests on the load-bearing system, but excludes VAT and non-structural tests, which the contractor arranges.

The practical read. Supervision is a small, legally fixed percentage of build cost. If a developer says it was “waived” or “handled internally” on a permitted building above the exemption thresholds, that is not a cost saving — it describes a building that was not lawfully supervised.

We have deliberately not quoted the ministry’s per-square-metre unit costs. They are revised annually and we could not verify the current figures against an official publication while writing, so the percentages above are the reliable part. Ask your lawyer or the supervision firm for the unit cost actually applied to your building.

2026

What Law 7579 changed in May 2026

The most recent amendment, Law No. 7579 of 7 May 2026, extended the regime into two areas that had sat outside it. Both matter if you are buying off-plan.

First, it created the zemin ve temel etüt kuruluşu — the soil and foundation survey organisation. Under the new Additional Article 2, such surveys for buildings within the law’s scope must be carried out by organisations holding a ministry permit, with at least one partner who is a geology, geophysics or civil engineer. Contracts are signed with the project designer or the owner, and the fee goes into a trust-type account on the supervision model, with 2% to the permitting authority, 2% to the ministry’s revolving fund and a ministry-set share of up to 10% to a designated body.

The enforcement is sharp. An administrative fine of 200,000 Turkish lira applies where such an organisation fails to follow the standards in its field or borehole work, sampling, storage, transport, laboratory delivery and reporting, or uses a laboratory without a ministry permit. If it issues a soil report contrary to the facts, or one that causes the static calculations to be made incorrectly, its permit is cancelled, its activity ended and its security forfeited — and its partners are barred from a technical role in any survey, supervision or laboratory organisation for three years. Implementation begins in a pilot province the ministry designates.

Second, the same law brought the beton üreticisi — the concrete producer, defined as the party that mixes concrete’s components and arranges its delivery — into the law’s definitions and into its monitoring and penalty provisions.

For the survey itself and what a soil report contains, see our guide to the zemin etüdü (soil survey) in Turkey. For how building age maps onto Turkey’s earthquake codes, see building age and earthquake codes.
بررسی موشکافانه

Turning all of this into five questions

You are not going to audit a construction file from abroad, and you do not need to. The value of understanding the system is that it tells you which five questions separate a building with a documented chain of responsibility from one without.

  • Was this building inside Law 4708 at all? Check the storey count and total construction area against the 200 m² and two-storey thresholds, and whether other buildings share the parcel.
  • Which firm supervised it, and is it still licensed? It is named in the supervision contract and in the permitting authority’s file. A firm whose permit was later cancelled is a materially different counterparty from one still trading.
  • Does an occupancy permit exist, and what is its date? That date starts both liability periods, and separately it is what makes the building lawfully habitable.
  • Is there a building identity certificate? For buildings completed since the 2022 amendment it should be affixed to the building.
  • Were any substantial alterations since the permit authorised? Unauthorised structural alteration shifts liability onto whoever did it, and is common in older resales.

Buying before completion shifts the questions: the supervision company is being appointed during your purchase rather than years before it, so the contract, the fee deposit and the undertaking are all live documents you can ask to see. See buying off-plan property in Turkey و new build versus resale for that timing, and kat irtifakı versus kat mülkiyeti for the ownership form you hold at each stage.

Please confirm current figures before relying on them. The rates, thresholds and penalties above come from the consolidated text of Law 4708 published by Turkey’s official legislation database and retrieved on 30 October 2026, including amendments up to Law 7579 of 7 May 2026. Turkish construction legislation changes frequently, ministry unit costs are revised annually, and the pilot-province rollout of the soil survey regime means some provisions apply unevenly. Confirm anything you intend to act on with a licensed Turkish lawyer, a chartered surveyor or the relevant ministry directorate before you commit.

Want the build quality checked, not just the title?

We pull the supervision record, the occupancy permit and the parcel file before you commit to a new build.

Speak to Our Team →
سوالات متداول

Yapı denetimi — frequently asked questions

What foreign buyers ask about building supervision, liability and which buildings are covered.

What is yapı denetimi in Turkey?+
Yapı denetimi is Turkey's statutory building supervision system, created by Law No. 4708 of 29 June 2001 and published in the Official Gazette on 13 July 2001. Buildings within its scope must be supervised by a yapı denetim kuruluşu — an independent company that holds a permit from the Ministry of Environment, Urbanisation and Climate Change, does supervision work and nothing else, and whose paid-in registered capital belongs entirely to architects and engineers. It reviews the soil reports and drawings before construction, supervises the work against the permit, has materials tested at licensed laboratories, and reports completion to the permitting authority. Crucially, it is contracted and paid by the building owner, not by the contractor.
How long is a building supervision company liable for defects?+
Under Article 3 of Law 4708, liability runs from the date the occupancy permit was obtained and lasts fifteen years for the building's load-bearing system and two years for the non-load-bearing parts. The supervision company, its inspecting architects and engineers, the project designers, the laboratory staff and the contractor are liable together, in proportion to their respective fault, towards both the building owner and the permitting authority. Because the clock starts at the occupancy permit rather than at your purchase, a resale apartment still carries whatever remains of that fifteen-year period — which makes the occupancy permit date worth establishing precisely before you buy.
Are small villas in Turkey covered by the building supervision law?+
Often not, and this is the exemption most worth checking. Article 1 of Law 4708 excludes detached buildings of no more than two storeys above the basement whose total construction area does not exceed 200 square metres. In village settlement areas and in municipalities with a population under 5,000 the exemption is wider still: up to two storeys and 500 square metres for housing. Such buildings still need a construction permit and an occupancy permit, and technical responsibility is assumed by an architect or engineer under the Development Law — but no licensed supervision company carries the fifteen-year statutory liability. One counterweight: where a parcel holds several detached buildings whose combined construction area exceeds 200 square metres, the law applies anyway.
Who chooses the building supervision company — the owner or the state?+
It depends on size, and the rule was rewritten by Law 7534 on 5 December 2024. Where the construction area on which the contract fee is based is up to 500 square metres, the owner selects the firm. For larger buildings the ministry determines up to two firms electronically, ranked first and second, taking into account how many are active in that province, and the owner contracts with one of them. In both cases the contract is between the firm and the building owner or the owner's proxy — and Article 2 expressly prevents the owner from appointing the contractor they hired for the construction work as that proxy, so the party being inspected cannot arrange its own inspection.
How much does yapı denetimi cost in Turkey?+
Article 5 fixes the rates rather than leaving them to negotiation. The fee is a percentage of the building's fee-basis approximate cost: 1.75% where the fee-basis construction area is up to and including 1,000 square metres, 1.5% from 1,001 up to and including 50,000 square metres, and 1.25% above that. For work not subject to electronic allocation the rate can be raised to a maximum of 3.50%, and it increases by 5% annually where construction runs beyond one year. Strengthening works cannot be charged at less than 25% of the whole-building fee. The owner pays into a trust-type account at the provincial accounting unit, 3% goes to the permitting authority and 3% to the ministry's revolving fund, and the firm may not request any further payment under another heading. The per-square-metre unit costs the percentages apply to are set by ministry regulation and revised annually, so ask for the figure actually used on your building.
What changed in Turkish building supervision law in 2026?+
Law No. 7579, dated 7 May 2026, extended the regime in two directions. It created the zemin ve temel etüt kuruluşu, a licensed soil and foundation survey organisation with at least one geology, geophysics or civil engineer among its partners. Under the new Additional Article 2, soil and foundation surveys for buildings within the law's scope must be carried out by such organisations, and implementation starts in a pilot province the ministry designates. Breaches of the standards for borehole work, sampling, transport or reporting, or using a laboratory without a ministry permit, attract an administrative fine of 200,000 Turkish lira; a report contrary to the facts, or one causing the static calculations to be made incorrectly, results in cancellation of the permit and a three-year bar on its partners holding technical roles. The same law also brought the beton üreticisi — the concrete producer — into the law's definitions, monitoring system and penalties.
Keep Reading

Where to go next

The rest of our foreign-buyer library, from the title deed itself to the build quality behind it.

با اطمینان خرید کنید

Have the supervision record checked before you commit

Tell us the building you are considering and we will establish whether it was supervised under Law 4708, which firm held the file, when the occupancy permit was issued and what remains of the statutory liability period. We work with licensed Turkish conveyancers and surveyors.